Pump station design and contract administration for Glenmore-Ellison Improvement District
Glenmore-Ellison Improvement District
The project was completed with Agua Consulting Inc. It included the conceptual and detailed design of a 3-storey pump station drawing water from Okanagan Lake. The station houses four 700 hp multi-stage pumps installed above steel caissons adjacent to Okanagan Lake. The station was designed with additional berths for future expansion.
In addition to design services, our team members acted as contract administrators during construction, as well as owner representatives and professional coordinator of a multi-disciplinary team involved in the project.